Public dossier Ferreira do Alentejo · Portugal Updated 16.10.2026

BioGreen LNG: Ferreira do Alentejo biomethane plant

In licensing Environmental impact assessment; revised project in public consultation until 20 March 2026; no decision found. approximate location

A Capwatt and Nutrifarms plant for about 67.2 GWh/yr of liquefied biomethane from livestock effluent and olive by-products. It is more than 2.7 km from Figueira dos Cavaleiros.

What we know

PromoterCapwatt Biometano Ferreira do Alentejo (Capwatt com a Nutrifarms / Sociedade Agrícola Vale de Ouro)
LocationFigueira dos Cavaleiros (Herdade do Marmelo), Ferreira do Alentejo (Beja)
Capacity ≈ 67.2 GWh/yr (liquefied biomethane)
Feedstock Livestock effluent, olive pomace and olive wash water
Distance to the village > 2.7 km

The announced investment is €25 million, with €2,550,000 of PRR support. After a request for more information, the revised project went back to public consultation from 2 February to 20 March 2026. We found no organised opposition and no environmental impact declaration.

What has happened

  1. PRR funding
    €2,550,000 on the final list.

  2. Consultation on the revised project
    Until 20 March 2026.

On the map

Documents and links

All projects See the sources

Sources on this page

  1. Unidade de biometano de 25ME em Ferreira do Alentejo em consulta pública Agroportal / Lusa · 13 Mar 2026
  2. Comunicado 02/2024 – AAC 02/C14-i01/2023 Fundo Ambiental · 2024-11
  3. Ferreira do Alentejo: projeto entra em consulta pública após revisão SAPO · 2026-02