Four months on, still no public consultation

We checked on 16 October: we found no environmental impact assessment or public consultation for the Guarda plant.

On 16 October 2026 we searched the Participa portal and found no public consultation or environmental impact assessment for the biomethane plant between Avelãs de Ambom and Pêra do Moço.

The Câmara's minutes and decisions of 24 August, 11 and 28 September and 12 October make no mention of biomethane. The latest official information is still that of 10 August, when the mayor said the project "is no more than an intention" and that the Câmara has no further information.

We keep watching. If you want to request the documents, use the letter template in the dossier.

Sign the petition All news

Sources on this page

  1. Participa: portal de consultas públicas (pesquisa de consultas para este projeto) Participa.gov.pt · consultado em 16.10.2026
  2. Portal de dados abertos da Câmara Municipal da Guarda: listagem de atas e deliberações Câmara Municipal da Guarda · consultado em 16.10.2026
  3. Ata da reunião ordinária da Câmara Municipal da Guarda de 10 de agosto de 2026 Câmara Municipal da Guarda · 10 Aug 2026